An addition error in your contractor’s quote works in your favor. Contractor quote rights in Belgium depend on the type of mistake, and judges do not always agree on whether you can insist on having the work done at the quoted price.

A contractor can make a mistake when adding up the individual items in a quote. The result: the quoted total is lower than the sum of the itemized work. That is not necessarily a bargain for you, as our lawyer explains.
If the contractor discovers the mistake after completing the work, they might ask you to pay the recalculated amount, sending you a higher invoice than expected. Whether they can actually make you pay the difference is another matter.
Contractor quote rights in Belgium: the basic rule
The starting point is clear: a contractor is generally bound by their quote, provided you accepted it within its validity period.
Contractors usually set a deadline for accepting their offer. This prevents a customer from coming back long after the quote was issued and demanding the same terms, even though prices have risen in the meantime.
Before committing, check how long the quote remains valid too.
A pricing error does not necessarily change things
Even if the quote contains a mistake, the contractor is generally still bound by it. This applies, for example, if they accidentally listed the wrong price for certain materials.
There is an exception, however, when the error is obvious: in other words, when the quoted price clearly could only be a mistake. This could be the case if the contractor left out a zero and wrote €100 instead of €1,000.
A mistake does not automatically entitle the contractor to change the price. An obvious error, however, may change the situation.
Judges disagree on addition errors
When the mistake involves adding up the individual items in the quote, the answer is less clear-cut.
Some judges allow the contractor to correct the calculation and issue an invoice based on the correct total. Under this approach, the incorrect amount at the bottom of the quote does not prevent the contractor from claiming the correctly calculated sum.
Others consider the contractor generally bound by the quoted total, even if they made a mistake when adding up the individual items.
To avoid discovering the problem when the invoice arrives, it is best to check the sums before accepting the quote. A few minutes with a calculator could spare you an unpleasant surprise and a much longer discussion once the work is finished.