Canceling a building work contract in Belgium, or postponing the work, raises questions about your commitments. If you have signed with a contractor for work on your house or apartment, can you delay it or cancel it altogether? And what might you have to pay the contractor?

With the recent war in Iran and rising prices, you may prefer to postpone or even cancel the work you commissioned from a contractor. Your options depend on the contract and how you bring it to an end or agree to delay it.
An agreement is still an agreement
If you have signed a contract with a contractor, you must generally honor it. A contract is, by its nature, binding. There are exceptions, however: for example, your contract may include a condition precedent (condition suspensive) making it dependent on obtaining a loan. If that financing is ultimately refused, you can still withdraw from the contract.
The fact that a war is underway in Iran and that prices for many products are rising as a result does not change this. That situation is not, in itself, a valid reason to cancel the contract or unilaterally postpone the work.
In other words, an unfavorable economic climate alone, however worrying, does not allow you to go back on your commitment to the contractor. Once an agreement has been reached, it remains binding on both parties unless an exception is expressly provided for or you find a solution by mutual agreement.
Reaching a mutual agreement
You can, however, agree on different arrangements with the contractor. You can mutually agree to terminate the contract or put the work on hold for a few months.
The contractor may attach conditions to that arrangement. For example, they may require compensation or stipulate that a surcharge will apply if the work takes place later than planned.
If you reach this kind of agreement with a contractor, you are strongly advised to put it in writing. This will help avoid later arguments about exactly what you agreed to. A written record makes each party’s commitments clear and reduces the scope for disputes later.
Canceling a building work contract in Belgium
If your contractor refuses your request not to proceed with the work, you still have the right to terminate the building work contract (contrat d’entreprise) unilaterally. You do not have to justify that decision.
But if you take this route, the contractor is entitled to compensation. They can claim payment for work already completed, as well as compensation for everything they could have earned from the project.
The contractor must nevertheless prove the extent of their loss. They can also specify compensation in advance in your contract as a fixed amount, for example as a percentage of the value of the contract you signed with them.
So although you can end the contract on your own initiative, doing so has consequences. It can cost you a substantial sum, depending on how far the work has progressed and the loss the contractor can demonstrate.